RFQ RCCS Manpower Usage

Allied Signal

12 months to gather requirements
9 months to implement database (6 of them to train a new user)
3 months to implement Industry Pac drivers.
4 months to integrate and test - automation loops required tuning

Los Alamos

Negligible time to offer some support.

Notes

LANL had written the same drivers in parallel
Allied Signal thought that they would have been more effective using a PLC

Previous slide Next slide Back to first slide View graphic version