Subject: | Re: Base Release 3.14.11 Timetable |
From: | Ralph Lange <[email protected]> |
To: | Andrew Johnson <[email protected]> |
Cc: | Core-Talk <[email protected]> |
Date: | Tue, 07 Jul 2009 08:02:34 +0200 |
Hi,only one question (that came up looking at the current status of the 3.14 branch):
I noticed that the codeathon project of adding PINI states has been put into CVS. Is my impression correct, that the original motivation (having a PINI state that allows for PINI processing *after* Channel Access started) somehow disappeared from the radar, and there's still no PINI state with working CA links?
Andrew is correct: I will be between continents next week - probably with internet access from Thursday (at the BNL guest house), but in vacation busy searching for a place and buying cars until first week of August.
Cheers, Ralph Andrew Johnson wrote:
I admit this timetable has had little consultation, but I'm extending the normal timing by a week (while I'm in Korea) which I hope will provide some compensation. I suspect Ralph will be switching continents around this time, hopefully others will be able to make up for his absence. The APS needs a release before the end of August...2009-07-19 All CVS commits must be completed (Sunday evening) 2009-07-20 R3.14.11-pre1 released, testing/debugging commences 2009-08-03 -RC1 vs -pre2 decision and release 2009-08-10 Earliest possible R3.14.11 release date Do these dates seem reasonable? - Andrew