I will be working full time on APS operator requested changes
to the Alarm Handler during the month of February. Ned has
promised these changes by the end of February.
I probably will not be able to continue work on the R3.14
new release until March.
Janet
Marty Kraimer wrote:
Ralph Lange wrote:
Shifting the date to Feb 26 would allow me one day for HPUX testing
before I leave with fingers crossed that all additional fixes won't
create problems on that platform. In that case I would try to entirely
block my Feb 27 schedule for HPUX testing (that day is in the first week
of a major shutdown, so I should better know soon).
What do you think?
Lets make it the 25th. That is all commits must be done before going
home on the 25th of Feb.
Final regression testing can start Feb 26th.
Any other comments about the schedule?
Marty
- References:
- RE: R3.14.2 Jeff Hill
- Re: R3.14.2 Marty Kraimer
- Re: R3.14.2 schedule Ralph Lange
- Re: R3.14.2 schedule Marty Kraimer
- Navigate by Date:
- Prev:
Re: R3.14.2 schedule Marty Kraimer
- Next:
RE: EPICS Timer Roundoff Jeff Hill
- Index:
2002
<2003>
2004
2005
2006
2007
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
- Navigate by Thread:
- Prev:
Re: R3.14.2 schedule Marty Kraimer
- Next:
RE: R3.14.2 Kenneth Evans, Jr.
- Index:
2002
<2003>
2004
2005
2006
2007
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
|