All,
It is not possible to honor PP or NPP options; the put operation completes immediately but whether the destination record will process depends on the process passive attribute of the destination field.
Could I get a clarification that? The reason why is because earlier in the Passive Process section, it says that
It determines if the linked record should be processed before getting a value from an input link or after writing a value to an output link.
From what is described in the second section, it appears that we can specify PP or NPP in the OUT field of a record. However, in the first portion, it appears to say otherwise.
Thank you!
|
- Replies:
- Re: Question about OUTLINK from the manual Johnson, Andrew N. via Tech-talk
- Navigate by Date:
- Prev:
Re: Storing an array element as a scalar in a record Wang, Andrew via Tech-talk
- Next:
Re: Question about OUTLINK from the manual Johnson, Andrew N. via Tech-talk
- Index:
1994
1995
1996
1997
1998
1999
2000
2001
2002
2003
2004
2005
2006
2007
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
2018
2019
2020
<2021>
2022
2023
2024
- Navigate by Thread:
- Prev:
Re: Storing an array element as a scalar in a record Wang, Andrew via Tech-talk
- Next:
Re: Question about OUTLINK from the manual Johnson, Andrew N. via Tech-talk
- Index:
1994
1995
1996
1997
1998
1999
2000
2001
2002
2003
2004
2005
2006
2007
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
2018
2019
2020
<2021>
2022
2023
2024
|
ANJ, 07 Mar 2021 |
·
Home
·
News
·
About
·
Base
·
Modules
·
Extensions
·
Distributions
·
Download
·
·
Search
·
EPICS V4
·
IRMIS
·
Talk
·
Bugs
·
Documents
·
Links
·
Licensing
·
|